They are making progress on the first two duplexes for Oasis. Footings and foundations have been poured, backfill is completed, plumbing mains have been run, and cement slabs have been poured and are curing. Once the slabs have fully cured the framing will begin.
Just a reminder that we are in the process of raising $250,000 which is a matching grant. Would you consider a year-end gift to Oasis knowing that whatever you give will be doubled? You can make a donation online or by check. If you would like to make a donation by check please send an email to matt@villagetovillageintl.com and he will respond with instructions on how to do that.